Structure 60404000035637 · Grant County, OR

1647000 over Summit Creek

Carries 1647000 over Summit Creek, 16 RD E To 1647 - S 4.3 M.

Overall conditionGood

Set by its lowest-rated component: Substructure at 8 of 9.

How ratings work
Deck9/9 · Excellent
Superstructure9/9 · Excellent
Substructuresets the rating8/9 · Very Good
Channelnot part of overall9/9 · Excellent
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
CAR · 15 FT48 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 9/9Superstructure 9/9Substructure 8/9 · sets the rating

48 ft end to end. Lengths and the car on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a slab bridge.

Built20242 years old
Length47.9 ft14.6 m
Daily traffic10counted 2018
Last inspectedAugust 2024every 24 months

Location

StateOregon
CountyGrant
Location16 RD E To 1647 - S 4.3 M
Carries1647000
CrossesSummit Creek
Coordinates44.12757, -118.57826

Physical Characteristics

MaterialPrestressed Concrete
DesignSlab
Total Length47.9 ft (14.6 m)
Max Span45.6 ft (13.9 m)
Deck Width22.6 ft (6.9 m)
Deck Area100.7 sq m
Main Spans1
Year Built2024

Traffic

Avg Daily Traffic10 (2018)
Lanes On Bridge1

Inspection & Ownership

Last InspectionAugust 2024
Inspection FrequencyEvery 24 months
OwnerU.S. Forest Service
Historical SignificanceHistorical significance is not determined
Scour Critical5 — Stable for scour
Structure Number060404000035637

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.