Structure 17216 · Lee County, AL

2nd AVE Opelika over No. Southern Railroad

Carries 2nd AVE Opelika over No. Southern Railroad, 2nd AVE Rr.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 8 of 9.

How ratings work
Decksets the rating8/9 · Very Good
Superstructuresets the rating8/9 · Very Good
Substructuresets the rating8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT282 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 8/9Superstructure 8/9Substructure 8/9

282 ft end to end, longest span 141 ft: about 4 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built199828 years old
Length282.2 ft86 m
Daily traffic18,979counted 2023
Last inspectedDecember 2023every 24 months

Location

StateAlabama
CountyLee
Location2nd AVE Rr
Carries2nd AVE Opelika
CrossesNo. Southern Railroad
Coordinates32.01469, -85.40083

Physical Characteristics

MaterialSteel Continuous
DesignStringer/Multi-beam
Total Length282.2 ft (86 m)
Max Span141.1 ft (43 m)
Deck Width63.6 ft (19.4 m)
Deck Area1668.4 sq m
Main Spans2
Year Built1998

Traffic

Avg Daily Traffic18,979 (2023)
Truck Traffic8%
Lanes On Bridge2

Inspection & Ownership

Last InspectionDecember 2023
Inspection FrequencyEvery 24 months
OwnerCity/Municipal Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number017216

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges