Structure 47C60 751 · Marion County, OR

95th AVE NE over Pudding River

Carries 95th AVE NE over Pudding River, 018 M N State-howell P Jt.

Overall conditionFair

Set by its lowest-rated component: Substructure at 6 of 9.

How ratings work
Deck8/9 · Very Good
Superstructure8/9 · Very Good
Substructuresets the rating6/9 · Satisfactory
Channelnot part of overall5/9 · Fair
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
25 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 8/9Superstructure 8/9Substructure 6/9 · sets the rating

25 ft end to end. Lengths are drawn to scale; at this length a semi-truck would be a speck. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a slab bridge.

Built197155 years old
Length24.9 ft7.6 m
Daily traffic256counted 2020
Last inspectedAugust 2024every 24 months

Location

StateOregon
CountyMarion
Location018 M N State-howell P Jt
Carries95th AVE NE
CrossesPudding River
Coordinates44.95070, -122.86837

Physical Characteristics

MaterialWood or Timber
DesignSlab
Total Length24.9 ft (7.6 m)
Max Span23.0 ft (7 m)
Deck Width25.6 ft (7.8 m)
Deck Area59.3 sq m
Main Spans1
Year Built1971

Traffic

Avg Daily Traffic256 (2020)
Truck Traffic9%
Lanes On Bridge2

Inspection & Ownership

Last InspectionAugust 2024
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalUnknown
Structure Number47C60 751

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.