Structure 3994 · Coffee County, AL

Caroline Street over Beaver Dam Creek

Carries Caroline Street over Beaver Dam Creek, Elba.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure and Substructure at 5 of 9.

How ratings work
Decksets the rating5/9 · Fair
Superstructuresets the rating5/9 · Fair
Substructuresets the rating5/9 · Fair
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT228 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 5/9Superstructure 5/9Substructure 5/9

228 ft end to end, longest span 19 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a channel-beam bridge.

Built195175 years old
Length228.0 ft69.5 m
Daily traffic540counted 2018
Last inspectedMay 2024every 24 months

Location

StateAlabama
CountyCoffee
LocationElba
CarriesCaroline Street
CrossesBeaver Dam Creek
Coordinates31.41257, -86.07900

Physical Characteristics

MaterialConcrete
DesignChannel Beam
Total Length228.0 ft (69.5 m)
Max Span19.0 ft (5.8 m)
Deck Width25.3 ft (7.7 m)
Deck Area535.1 sq m
Main Spans12
Year Built1951

Traffic

Avg Daily Traffic540 (2018)
Truck Traffic1%
Lanes On Bridge2

Inspection & Ownership

Last InspectionMay 2024
Inspection FrequencyEvery 24 months
OwnerCity/Municipal Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical4 — Foundations need monitoring
Structure Number003994

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges