Structure 13429 · Pike County, MO

County RD 123 over Peno CR

Carries County RD 123 over Peno CR, S 1 T 54 N R 4 W.

Overall conditionGood

Set by its lowest-rated component: Superstructure and Substructure at 7 of 9.

How ratings work
Deck8/9 · Very Good
Superstructuresets the rating7/9 · Good
Substructuresets the rating7/9 · Good
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT183 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 8/9Superstructure 7/9 · sets the ratingSubstructure 7/9 · sets the rating

183 ft end to end, longest span 70 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built198739 years old
Length183.1 ft55.8 m
Daily traffic75counted 2023
Last inspectedJuly 2024every 24 months

Location

StateMissouri
CountyPike
LocationS 1 T 54 N R 4 W
CarriesCounty RD 123
CrossesPeno CR
Coordinates39.48850, -91.29569

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length183.1 ft (55.8 m)
Max Span69.9 ft (21.3 m)
Deck Width26.2 ft (8 m)
Deck Area446.4 sq m
Main Spans3
Year Built1987

Traffic

Avg Daily Traffic75 (2023)
Truck Traffic10%
Lanes On Bridge2

Inspection & Ownership

Last InspectionJuly 2024
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure Number13429

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.