Structure B47011000000000 · Pierce County, WI

Cth G over Rush River

Carries Cth G over Rush River, 0.1m S Jct Cth N To N.

Overall conditionGood

Set by its lowest-rated component: Deck at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructure8/9 · Very Good
Substructure8/9 · Very Good
Channelnot part of overall7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT158 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9 · sets the ratingSuperstructure 8/9Substructure 8/9

158 ft end to end, longest span 52 ft: about 2 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built199333 years old
Length158.1 ft48.2 m
Daily traffic224counted 2022
Last inspectedApril 2023every 24 months

Location

StateWisconsin
CountyPierce
Location0.1m S Jct Cth N To N
CarriesCth G
CrossesRush River
Coordinates44.76860, -92.34380

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length158.1 ft (48.2 m)
Max Span51.8 ft (15.8 m)
Deck Width32.2 ft (9.8 m)
Deck Area472.4 sq m
Main Spans3
Year Built1993

Traffic

Avg Daily Traffic224 (2022)
Truck Traffic14%
Lanes On Bridge2

Inspection & Ownership

Last InspectionApril 2023
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure NumberB47011000000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.