Structure E-470-05.13A · Douglas County, CO

E-470 NB over Cherry Creek

Carries E-470 NB over Cherry Creek, 5.13 Mi From I25.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructuresets the rating7/9 · Good
Substructuresets the rating7/9 · Good
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT608 FT OVERALL100 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 7/9Substructure 7/9

608 ft end to end, longest span 157 ft: about 1.7 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a box-beam bridge.

Built1996rebuilt 2017
Length607.9 ft185.3 m
Daily traffic24,407counted 2018
Last inspectedAugust 2024every 24 months

Location

StateColorado
CountyDouglas
Location5.13 Mi From I25
CarriesE-470 NB
CrossesCherry Creek
Coordinates39.54975, -104.77980

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignBox Beam - Multiple
Total Length607.9 ft (185.3 m)
Max Span157.2 ft (47.9 m)
Deck Width74.1 ft (22.6 m)
Deck Area4187.8 sq m
Main Spans4
Year Built1996 (reconstructed 2017)

Traffic

Avg Daily Traffic24,407 (2018)
Truck Traffic6%
Lanes On Bridge3

Inspection & Ownership

Last InspectionAugust 2024
Inspection FrequencyEvery 24 months
OwnerLocal Toll Authority
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure NumberE-470-05.13A

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.