Structure E-470-34.79B · Adams County, CO

E-470 SB over Burlington Ditch

Carries E-470 SB over Burlington Ditch, 34.79 Mi From I25.

Overall conditionFair

Set by its lowest-rated component: Substructure at 6 of 9.

How ratings work
Deck7/9 · Good
Superstructure7/9 · Good
Substructuresets the rating6/9 · Satisfactory
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT183 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 7/9Substructure 6/9 · sets the rating

183 ft end to end, longest span 99 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built200224 years old
Length183.1 ft55.8 m
Daily traffic22,442counted 2018
Last inspectedJuly 2023every 24 months

Location

StateColorado
CountyAdams
Location34.79 Mi From I25
CarriesE-470 SB
CrossesBurlington Ditch
Coordinates39.92071, -104.79300

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length183.1 ft (55.8 m)
Max Span99.1 ft (30.2 m)
Deck Width40.0 ft (12.2 m)
Deck Area680.8 sq m
Main Spans2
Year Built2002

Traffic

Avg Daily Traffic22,442 (2018)
Truck Traffic6%
Lanes On Bridge2

Inspection & Ownership

Last InspectionJuly 2023
Inspection FrequencyEvery 24 months
OwnerLocal Toll Authority
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure NumberE-470-34.79B

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.