Overall conditionGood

Set by its lowest-rated component: Deck and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructure8/9 · Very Good
Substructuresets the rating7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
CAR · 15 FT69 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9 · sets the ratingSuperstructure 8/9Substructure 7/9 · sets the rating

69 ft end to end. Lengths and the car on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built200917 years old
Length68.9 ft21 m
Daily traffic12,260counted 2022
Last inspectedApril 2022every 48 months

Location

StateConnecticut
CountyFairfield
LocationEagle Road Shopping Cntr
CarriesEagle Road
CrossesInternational Drive
Coordinates41.41905, -73.41824

Physical Characteristics

MaterialSteel
DesignStringer/Multi-beam
Total Length68.9 ft (21 m)
Max Span64.0 ft (19.5 m)
Deck Width44.0 ft (13.4 m)
Deck Area281.4 sq m
Main Spans1
Year Built2009

Traffic

Avg Daily Traffic12,260 (2022)
Truck Traffic4%
Lanes On Bridge2
Lanes Under Bridge2

Inspection & Ownership

Last InspectionApril 2022
Inspection FrequencyEvery 48 months
OwnerTown/Township Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number06775

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.