Structure 12007500000000 · Clark County, IL

Fas 1707 over East Mill Creek

Carries Fas 1707 over East Mill Creek, 2 Mi. W Marshall.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 9 of 9.

How ratings work
Decksets the rating9/9 · Excellent
Superstructuresets the rating9/9 · Excellent
Substructuresets the rating9/9 · Excellent
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT167 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 9/9Superstructure 9/9Substructure 9/9

167 ft end to end, longest span 69 ft: about 2 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built20233 years old
Length166.7 ft50.8 m
Daily traffic3,200counted 2023
Last inspectedAugust 2023every 24 months

Location

StateIllinois
CountyClark
Location2 Mi. W Marshall
CarriesFas 1707
CrossesEast Mill Creek
Coordinates39.37960, -87.73588

Physical Characteristics

MaterialSteel Continuous
DesignStringer/Multi-beam
Total Length166.7 ft (50.8 m)
Max Span69.2 ft (21.1 m)
Deck Width38.7 ft (11.8 m)
Deck Area599.4 sq m
Main Spans3
Year Built2023

Traffic

Avg Daily Traffic3,200 (2023)
Truck Traffic8%
Lanes On Bridge2

Inspection & Ownership

Last InspectionAugust 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure Number012007500000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.