Overall conditionGood

Set by its lowest-rated component: Deck and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructure8/9 · Very Good
Substructuresets the rating7/9 · Good
Channelnot part of overall5/9 · Fair
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT180 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9 · sets the ratingSuperstructure 8/9Substructure 7/9 · sets the rating

180 ft end to end, longest span 60 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1960rebuilt 2005
Length180.1 ft54.9 m
Daily traffic12,110counted 2005
Last inspectedNovember 2023every 24 months

Location

StateMichigan
CountySt. Clair
LocationPvt Clm 306 ST Clair Twp
CarriesFred Moore HWY
CrossesPine River
Coordinates42.81722, -82.51076

Physical Characteristics

MaterialSteel Continuous
DesignStringer/Multi-beam
Total Length180.1 ft (54.9 m)
Max Span60.0 ft (18.3 m)
Deck Width39.7 ft (12.1 m)
Deck Area664.3 sq m
Main Spans3
Year Built1960 (reconstructed 2005)

Traffic

Avg Daily Traffic12,110 (2005)
Truck Traffic9%
Lanes On Bridge3

Inspection & Ownership

Last InspectionNovember 2023
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure Number000000000010042

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.