Structure F-17-DY · Arapahoe County, CO

I 225 Ml Nbnd over Cherry Creek

Carries I 225 Ml Nbnd over Cherry Creek, 3.1 Mi E Of I-25.

Overall conditionFair

Set by its lowest-rated component: Deck and Substructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructure7/9 · Good
Substructuresets the rating6/9 · Satisfactory
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT235 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9 · sets the ratingSuperstructure 7/9Substructure 6/9 · sets the rating

235 ft end to end, longest span 114 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1971rebuilt 2007
Length234.9 ft71.6 m
Daily traffic68,000counted 2020
Last inspectedJune 2023every 24 months

Location

StateColorado
CountyArapahoe
Location3.1 Mi E Of I-25
CarriesI 225 Ml Nbnd
CrossesCherry Creek
Coordinates39.65276, -104.85680

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length234.9 ft (71.6 m)
Max Span113.8 ft (34.7 m)
Deck Width80.7 ft (24.6 m)
Deck Area1761.4 sq m
Main Spans2
Year Built1971 (reconstructed 2007)

Traffic

Avg Daily Traffic68,000 (2020)
Truck Traffic6%
Lanes On Bridge4

Inspection & Ownership

Last InspectionJune 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure NumberF-17-DY

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.