Structure 720706 · Duval County, FL

I-295 (sr-9a) NB over I-295 (sr-9a)

Carries I-295 (sr-9a) NB over I-295 (sr-9a), (i-295) NB To SR 202 WB.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructuresets the rating7/9 · Good
Substructuresets the rating7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT326 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 7/9Substructure 7/9

326 ft end to end, longest span 186 ft: about 5 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a box-beam bridge.

Built200719 years old
Length325.8 ft99.3 m
Daily traffic28,000counted 2023
Last inspectedApril 2024every 24 months

Location

StateFlorida
CountyDuval
Location(i-295) NB To SR 202 WB
CarriesI-295 (sr-9a) NB
CrossesI-295 (sr-9a)
Coordinates30.25489, -81.51672

Physical Characteristics

MaterialSteel Continuous
DesignBox Beam - Single/Spread
Total Length325.8 ft (99.3 m)
Max Span186.4 ft (56.8 m)
Deck Width36.1 ft (11 m)
Deck Area1092.3 sq m
Main Spans2
Year Built2007

Traffic

Avg Daily Traffic28,000 (2023)
Truck Traffic13%
Lanes On Bridge1
Lanes Under Bridge8

Inspection & Ownership

Last InspectionApril 2024
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number720706

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges