Structure 120191 · Lee County, FL

I-75 SB over Hicks Crossing

Carries I-75 SB over Hicks Crossing, 1.2mi N Of Corkscrew RD.

Overall conditionGood

Set by its lowest-rated component: Substructure at 7 of 9.

How ratings work
Deck8/9 · Very Good
Superstructure8/9 · Very Good
Substructuresets the rating7/9 · Good
Channelnot part of overall7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT136 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 8/9Superstructure 8/9Substructure 7/9 · sets the rating

136 ft end to end, longest span 34 ft. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a slab bridge.

Built200917 years old
Length136.2 ft41.5 m
Daily traffic58,500counted 2023
Last inspectedOctober 2023every 24 months

Location

StateFlorida
CountyLee
Location1.2mi N Of Corkscrew RD
CarriesI-75 SB
CrossesHicks Crossing
Coordinates26.44942, -81.78423

Physical Characteristics

MaterialConcrete Continuous
DesignSlab
Total Length136.2 ft (41.5 m)
Max Span34.1 ft (10.4 m)
Deck Width67.9 ft (20.7 m)
Deck Area859.0 sq m
Main Spans4
Year Built2009

Traffic

Avg Daily Traffic58,500 (2023)
Truck Traffic12%
Lanes On Bridge3

Inspection & Ownership

Last InspectionOctober 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure Number120191

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.