Structure PD0000000 · Benton County, WA

I-82 over Columbia River

Carries I-82 over Columbia River, 1.0 E Jct SR 14.

Overall conditionFair

Set by its lowest-rated component: Superstructure at 6 of 9.

How ratings work
Deck7/9 · Good
Superstructuresets the rating6/9 · Satisfactory
Substructure7/9 · Good
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT3,380 FT OVERALL500 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 6/9 · sets the ratingSubstructure 7/9

3,380 ft end to end, longest span 600 ft: about 9.4 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a through truss.

Built1955rebuilt 1990
Length3379.9 ft1030.2 m
Daily traffic12,770counted 2023
Last inspectedJune 2023every 24 months

Location

StateWashington
CountyBenton
Location1.0 E Jct SR 14
CarriesI-82
CrossesColumbia River
Coordinates45.93494, -119.33033

Physical Characteristics

MaterialSteel Continuous
DesignTruss - Thru
Total Length3379.9 ft (1030.2 m)
Max Span600.1 ft (182.9 m)
Deck Width30.2 ft (9.2 m)
Deck Area9477.8 sq m
Main Spans5
Year Built1955 (reconstructed 1990)

Traffic

Avg Daily Traffic12,770 (2023)
Truck Traffic22%
Lanes On Bridge2

Inspection & Ownership

Last InspectionJune 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is possibly eligible (requires evaluation)
Scour Critical5 — Stable for scour
Structure Number000000PD0000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.