Structure B166598MDDOTNBI · Suffolk County, MA

I 93 Ramp Xx over HWY Hov EB

Carries I 93 Ramp Xx over HWY Hov EB, 2.5 M E. Of 193 NB.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure and Substructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructuresets the rating6/9 · Satisfactory
Substructuresets the rating6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT701 FT OVERALL100 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 6/9Substructure 6/9

701 ft end to end, longest span 158 ft: about 1.9 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a segmental box-girder bridge.

Built200125 years old
Length701.1 ft213.7 m
Daily traffic4,578counted 2019
Last inspectedJanuary 2022every 24 months

Location

StateMassachusetts
CountySuffolk
Location2.5 M E. Of 193 NB
CarriesI 93 Ramp Xx
CrossesHWY Hov EB
Coordinates42.34392, -71.06133

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignSegmental Box Girder
Total Length701.1 ft (213.7 m)
Max Span157.8 ft (48.1 m)
Deck Width24.6 ft (7.5 m)
Deck Area1602.8 sq m
Main Spans5
Year Built2001

Traffic

Avg Daily Traffic4,578 (2019)
Truck Traffic5%
Lanes On Bridge2
Lanes Under Bridge2

Inspection & Ownership

Last InspectionJanuary 2022
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceHistorical significance is not determined
Scour CriticalNot applicable
Structure NumberB166598MDDOTNBI

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.