Structure 5086 · Chesterfield County, VA

I-95 over Route 10

Carries I-95 over Route 10, 3.05 Fr 620 & 1.61 To 288.

Overall conditionFair

Set by its lowest-rated component: Superstructure and Substructure at 5 of 9.

How ratings work
Deck6/9 · Satisfactory
Superstructuresets the rating5/9 · Fair
Substructuresets the rating5/9 · Fair
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT166 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 5/9 · sets the ratingSubstructure 5/9 · sets the rating

166 ft end to end, longest span 51 ft: about 2 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1958rebuilt 1996
Length166.3 ft50.7 m
Daily traffic125,320counted 2022
Last inspectedMarch 2024every 24 months

Location

StateVirginia
CountyChesterfield
Location3.05 Fr 620 & 1.61 To 288
CarriesI-95
CrossesRoute 10
Coordinates37.35434, -77.40456

Physical Characteristics

MaterialSteel
DesignStringer/Multi-beam
Total Length166.3 ft (50.7 m)
Max Span51.2 ft (15.6 m)
Deck Width148.0 ft (45.1 m)
Deck Area2286.6 sq m
Main Spans4
Year Built1958 (reconstructed 1996)

Traffic

Avg Daily Traffic125,320 (2022)
Truck Traffic1%
Lanes On Bridge8
Lanes Under Bridge6

Inspection & Ownership

Last InspectionMarch 2024
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number000000000005086

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.