Structure 870363 · Miami-Dade County, FL

I-95 To Sr-836 WB over NW 7th AVE & Salrr

Carries I-95 To Sr-836 WB over NW 7th AVE & Salrr, Midtown Interchange.

Overall conditionFair

Set by its lowest-rated component: Superstructure at 6 of 9.

How ratings work
Deck7/9 · Good
Superstructuresets the rating6/9 · Satisfactory
Substructure7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT532 FT OVERALL100 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 6/9 · sets the ratingSubstructure 7/9

532 ft end to end, longest span 90 ft: about 7 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1969rebuilt 1994
Length532.2 ft162.2 m
Daily traffic39,500counted 2022
Last inspectedMay 2023every 24 months

Location

StateFlorida
CountyMiami-Dade
LocationMidtown Interchange
CarriesI-95 To Sr-836 WB
CrossesNW 7th AVE & Salrr
Coordinates25.78944, -80.20639

Physical Characteristics

MaterialPrestressed Concrete
DesignStringer/Multi-beam
Total Length532.2 ft (162.2 m)
Max Span89.9 ft (27.4 m)
Deck Width41.3 ft (12.6 m)
Deck Area2043.7 sq m
Main Spans7
Year Built1969 (reconstructed 1994)

Traffic

Avg Daily Traffic39,500 (2022)
Truck Traffic10%
Lanes On Bridge3
Lanes Under Bridge5

Inspection & Ownership

Last InspectionMay 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number870363

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.