Structure 150150007212206 · Bexar County, TX

IH 10 WB Upper Lev over Fredericksburg - Poplar

Carries IH 10 WB Upper Lev over Fredericksburg - Poplar, Mulberry To Frio ST.

Overall conditionFair

Set by its lowest-rated component: Substructure at 5 of 9.

How ratings work
Deck6/9 · Satisfactory
Superstructure6/9 · Satisfactory
Substructuresets the rating5/9 · Fair
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
8,955 FT OVERALL1,000 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 6/9Substructure 5/9 · sets the rating

8,955 ft end to end, longest span 110 ft: about 25 football fields, or 1.7 miles. Lengths are drawn to scale; at this length a semi-truck would be a speck. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a segmental box-girder bridge.

Built198937 years old
Length8955.1 ft2729.5 m
Daily traffic81,813counted 2023
Last inspectedJuly 2024every 24 months

Location

StateTexas
CountyBexar
LocationMulberry To Frio ST
CarriesIH 10 WB Upper Lev
CrossesFredericksburg - Poplar
Coordinates29.44289, -98.51438

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignSegmental Box Girder
Total Length8955.1 ft (2729.5 m)
Max Span109.9 ft (33.5 m)
Deck Width60.7 ft (18.5 m)
Deck Area50495.8 sq m
Main Spans68
Year Built1989

Traffic

Avg Daily Traffic81,813 (2023)
Truck Traffic6%
Lanes On Bridge3
Lanes Under Bridge24

Inspection & Ownership

Last InspectionJuly 2024
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number150150007212206

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.