Structure 57 0566L · San Diego County, CA

Interstate 5 SB over San Diego Riv Friars RD

Carries Interstate 5 SB over San Diego Riv Friars RD, 11-sd-005-r20.12-sd.

Overall conditionFair

Set by its lowest-rated component: Deck at 5 of 9.

How ratings work
Decksets the rating5/9 · Fair
Superstructure7/9 · Good
Substructure7/9 · Good
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT927 FT OVERALL200 FT0ELEVATION · LENGTHS TO SCALE
Deck 5/9 · sets the ratingSuperstructure 7/9Substructure 7/9

927 ft end to end, longest span 95 ft: about 2.6 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a box-beam bridge.

Built196957 years old
Length926.8 ft282.5 m
Daily traffic99,500counted 2020
Last inspectedSeptember 2023every 24 months

Location

StateCalifornia
CountySan Diego
Location11-sd-005-r20.12-sd
CarriesInterstate 5 SB
CrossesSan Diego Riv Friars RD
Coordinates32.76000, -117.20413

Physical Characteristics

MaterialConcrete Continuous
DesignBox Beam - Multiple
Total Length926.8 ft (282.5 m)
Max Span95.1 ft (29 m)
Deck Width75.1 ft (22.9 m)
Deck Area6469.2 sq m
Main Spans10
Year Built1969

Traffic

Avg Daily Traffic99,500 (2020)
Truck Traffic5%
Lanes On Bridge4
Lanes Under Bridge4

Inspection & Ownership

Last InspectionSeptember 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure Number57 0566L

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.