Structure 19 0056 · Placer County, CA

Interstate 80 over Miners Ravine

Carries Interstate 80 over Miners Ravine, 03-pla-080-2.88-rsv.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructuresets the rating7/9 · Good
Substructuresets the rating7/9 · Good
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT234 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 7/9Substructure 7/9

234 ft end to end, longest span 88 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a tee-beam bridge.

Built1954rebuilt 2008
Length233.9 ft71.3 m
Daily traffic155,000counted 2009
Last inspectedOctober 2023every 24 months

Location

StateCalifornia
CountyPlacer
Location03-pla-080-2.88-rsv
CarriesInterstate 80
CrossesMiners Ravine
Coordinates38.75579, -121.26289

Physical Characteristics

MaterialConcrete Continuous
DesignTee Beam
Total Length233.9 ft (71.3 m)
Max Span87.9 ft (26.8 m)
Deck Width135.8 ft (41.4 m)
Deck Area2951.8 sq m
Main Spans3
Year Built1954 (reconstructed 2008)

Traffic

Avg Daily Traffic155,000 (2009)
Truck Traffic6%
Lanes On Bridge10

Inspection & Ownership

Last InspectionOctober 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure Number19 0056

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.