Structure 4803795 · Lucas County, OH

Ir 75 over Berdan Ottawa R. Us24 CR

Carries Ir 75 over Berdan Ottawa R. Us24 CR, 1.05 Mi. N. Of I-475.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 8 of 9.

How ratings work
Decksets the rating8/9 · Very Good
Superstructuresets the rating8/9 · Very Good
Substructuresets the rating8/9 · Very Good
Channelnot part of overall7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT2,010 FT OVERALL250 FT0ELEVATION · LENGTHS TO SCALE
Deck 8/9Superstructure 8/9Substructure 8/9

2,010 ft end to end, longest span 160 ft: about 5.6 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built20188 years old
Length2010.2 ft612.7 m
Daily traffic61,427counted 2014
Last inspectedAugust 2023every 24 months

Location

StateOhio
CountyLucas
Location1.05 Mi. N. Of I-475
CarriesIr 75
CrossesBerdan Ottawa R. Us24 CR
Coordinates41.68846, -83.56238

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length2010.2 ft (612.7 m)
Max Span160.4 ft (48.9 m)
Deck Width77.1 ft (23.5 m)
Deck Area14398.5 sq m
Main Spans14
Year Built2018

Traffic

Avg Daily Traffic61,427 (2014)
Truck Traffic21%
Lanes On Bridge4
Lanes Under Bridge6

Inspection & Ownership

Last InspectionAugust 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure Number4803795

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.