Structure 72470900000000 · Peoria County, IL

Legion Hall RD over Kickapoo Creek

Carries Legion Hall RD over Kickapoo Creek, Sw-12-t10nr7e.

Overall conditionFair

Set by its lowest-rated component: Deck at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructure7/9 · Good
Substructure7/9 · Good
Channelnot part of overall5/9 · Fair
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
CAR · 15 FT118 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9 · sets the ratingSuperstructure 7/9Substructure 7/9

118 ft end to end, longest span 44 ft. Lengths and the car on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built198046 years old
Length118.1 ft36 m
Daily traffic250counted 2022
Last inspectedSeptember 2024every 24 months

Location

StateIllinois
CountyPeoria
LocationSw-12-t10nr7e
CarriesLegion Hall RD
CrossesKickapoo Creek
Coordinates40.85666, -89.65624

Physical Characteristics

MaterialSteel Continuous
DesignStringer/Multi-beam
Total Length118.1 ft (36 m)
Max Span44.0 ft (13.4 m)
Deck Width25.9 ft (7.9 m)
Deck Area284.4 sq m
Main Spans3
Year Built1980

Traffic

Avg Daily Traffic250 (2022)
Truck Traffic6%
Lanes On Bridge2

Inspection & Ownership

Last InspectionSeptember 2024
Inspection FrequencyEvery 24 months
OwnerTown/Township Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure Number072470900000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges