Structure S080 06963 · Cheyenne County, NE

Link 17e & RD 135 over I80

Carries Link 17e & RD 135 over I80, Sunol Interchng.

Overall conditionGood

Set by its lowest-rated component: Deck and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructure8/9 · Very Good
Substructuresets the rating7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT276 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9 · sets the ratingSuperstructure 8/9Substructure 7/9 · sets the rating

276 ft end to end, longest span 89 ft: about 4 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1971rebuilt 2006
Length275.9 ft84.1 m
Daily traffic100counted 2018
Last inspectedOctober 2023every 24 months

Location

StateNebraska
CountyCheyenne
LocationSunol Interchng
CarriesLink 17e & RD 135
CrossesI80
Coordinates41.11300, -102.76350

Physical Characteristics

MaterialPrestressed Concrete
DesignStringer/Multi-beam
Total Length275.9 ft (84.1 m)
Max Span88.9 ft (27.1 m)
Deck Width43.0 ft (13.1 m)
Deck Area1101.7 sq m
Main Spans4
Year Built1971 (reconstructed 2006)

Traffic

Avg Daily Traffic100 (2018)
Truck Traffic20%
Lanes On Bridge2
Lanes Under Bridge4

Inspection & Ownership

Last InspectionOctober 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure NumberS080 06963

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.