Structure 53C082741400005 · Polk County, OR

Morrow Road over Rickreall Creek

Carries Morrow Road over Rickreall Creek, 0005 S Of County RD 7426.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure and Substructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructuresets the rating6/9 · Satisfactory
Substructuresets the rating6/9 · Satisfactory
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT142 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 6/9Substructure 6/9

142 ft end to end, longest span 54 ft. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a tee-beam bridge.

Built196066 years old
Length142.1 ft43.3 m
Daily traffic389counted 2020
Last inspectedAugust 2024every 24 months

Location

StateOregon
CountyPolk
Location0005 S Of County RD 7426
CarriesMorrow Road
CrossesRickreall Creek
Coordinates44.92885, -123.19723

Physical Characteristics

MaterialConcrete Continuous
DesignTee Beam
Total Length142.1 ft (43.3 m)
Max Span54.1 ft (16.5 m)
Deck Width28.9 ft (8.8 m)
Deck Area381.0 sq m
Main Spans3
Year Built1960

Traffic

Avg Daily Traffic389 (2020)
Truck Traffic10%
Lanes On Bridge2

Inspection & Ownership

Last InspectionAugust 2024
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalUnknown
Structure Number53C082741400005

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.