Structure S080 45308 · Douglas County, NE

Nb-us75/wb-i80 over I80/bn&up/i480/rmp 50

Carries Nb-us75/wb-i80 over I80/bn&up/i480/rmp 50, Grover ST Intrchg #8.

Overall conditionGood

Set by its lowest-rated component: Superstructure at 7 of 9.

How ratings work
Deck8/9 · Very Good
Superstructuresets the rating7/9 · Good
Substructure8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT1,995 FT OVERALL250 FT0ELEVATION · LENGTHS TO SCALE
Deck 8/9Superstructure 7/9 · sets the ratingSubstructure 8/9

1,995 ft end to end, longest span 175 ft: about 5.5 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1989rebuilt 1992
Length1995.1 ft608.1 m
Daily traffic84,810counted 2018
Last inspectedMarch 2024every 24 months

Location

StateNebraska
CountyDouglas
LocationGrover ST Intrchg #8
CarriesNb-us75/wb-i80
CrossesI80/bn&up/i480/rmp 50
Coordinates41.22810, -95.95370

Physical Characteristics

MaterialSteel Continuous
DesignStringer/Multi-beam
Total Length1995.1 ft (608.1 m)
Max Span174.9 ft (53.3 m)
Deck Width36.4 ft (11.1 m)
Deck Area6749.9 sq m
Main Spans14
Year Built1989 (reconstructed 1992)

Traffic

Avg Daily Traffic84,810 (2018)
Truck Traffic3%
Lanes On Bridge2
Lanes Under Bridge13

Inspection & Ownership

Last InspectionMarch 2024
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure NumberS080 45308

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.