Structure 1400433 · Morris County, NJ

Old Bloomfield AVE over Branch Ofpassaic River

Carries Old Bloomfield AVE over Branch Ofpassaic River, 0.09 Mi. North Of US 46.

Overall conditionPoor

Set by its lowest-rated component: Deck at 4 of 9.

How ratings work
Decksets the rating4/9 · Poor
Superstructure5/9 · Fair
Substructure5/9 · Fair
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT123 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 4/9 · sets the ratingSuperstructure 5/9Substructure 5/9

123 ft end to end, longest span 29 ft. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1921105 years old
Length123.0 ft37.5 m
Daily traffic328counted 2023
Last inspectedAugust 2023every 24 months

Location

StateNew Jersey
CountyMorris
Location0.09 Mi. North Of US 46
CarriesOld Bloomfield AVE
CrossesBranch Ofpassaic River
Coordinates40.85983, -74.32779

Physical Characteristics

MaterialSteel
DesignStringer/Multi-beam
Total Length123.0 ft (37.5 m)
Max Span28.9 ft (8.8 m)
Deck Width32.8 ft (10 m)
Deck Area375 sq m
Main Spans4
Year Built1921

Traffic

Avg Daily Traffic328 (2023)
Truck Traffic1%
Lanes On Bridge2

Inspection & Ownership

Last InspectionAugust 2023
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceHistorical significance is not determined
Scour Critical8 — Stable, low risk
Structure Number1400433

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.