Structure 86447000000000 · Spokane County, WA

Old Sr-195 over Spring Valley Creek

Carries Old Sr-195 over Spring Valley Creek, 100 Ft N Of Babb Road.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure and Substructure at 5 of 9.

How ratings work
Decksets the rating5/9 · Fair
Superstructuresets the rating5/9 · Fair
Substructuresets the rating5/9 · Fair
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
24 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 5/9Superstructure 5/9Substructure 5/9

24 ft end to end. Lengths are drawn to scale; at this length a semi-truck would be a speck. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a slab bridge.

Built193096 years old
Length24.0 ft7.3 m
Daily traffic506counted 2019
Last inspectedJune 2023every 24 months

Location

StateWashington
CountySpokane
Location100 Ft N Of Babb Road
CarriesOld Sr-195
CrossesSpring Valley Creek
Coordinates47.27952, -117.36183

Physical Characteristics

MaterialConcrete
DesignSlab
Total Length24.0 ft (7.3 m)
Max Span22.0 ft (6.7 m)
Deck Width27.9 ft (8.5 m)
Deck Area62.0 sq m
Main Spans1
Year Built1930

Traffic

Avg Daily Traffic506 (2019)
Truck Traffic19%
Lanes On Bridge2

Inspection & Ownership

Last InspectionJune 2023
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceHistorical significance is not determined
Scour CriticalUnknown
Structure Number086447000000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.