Structure 16522 160 00085 · Clackamas County, OR

Or 213 (hwy 160) over Redland RD & Creek

Carries Or 213 (hwy 160) over Redland RD & Creek, 2.9 Mi Off Oregon City Cc.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructuresets the rating6/9 · Satisfactory
Substructure7/9 · Good
Channelnot part of overall7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT265 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9 · sets the ratingSuperstructure 6/9 · sets the ratingSubstructure 7/9

265 ft end to end, longest span 135 ft: about 4 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a box-beam bridge.

Built198343 years old
Length265.1 ft80.8 m
Daily traffic45,021counted 2022
Last inspectedJune 2023every 24 months

Location

StateOregon
CountyClackamas
Location2.9 Mi Off Oregon City Cc
CarriesOr 213 (hwy 160)
CrossesRedland RD & Creek
Coordinates45.36125, -122.58214

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignBox Beam - Multiple
Total Length265.1 ft (80.8 m)
Max Span134.8 ft (41.1 m)
Deck Width75.5 ft (23 m)
Deck Area1858.4 sq m
Main Spans2
Year Built1983

Traffic

Avg Daily Traffic45,021 (2022)
Truck Traffic2%
Lanes On Bridge4
Lanes Under Bridge2

Inspection & Ownership

Last InspectionJune 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical7 — Countermeasures installed
Structure Number16522 160 00085

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.