Structure 7115 01WX00106 · Multnomah County, OR

Or 99w Ramp over B-153 N Interstate AVE

Carries Or 99w Ramp over B-153 N Interstate AVE, Btwn N Tillamook/hancock.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure and Substructure at 5 of 9.

How ratings work
Decksets the rating5/9 · Fair
Superstructuresets the rating5/9 · Fair
Substructuresets the rating5/9 · Fair
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT1,011 FT OVERALL200 FT0ELEVATION · LENGTHS TO SCALE
Deck 5/9Superstructure 5/9Substructure 5/9

1,011 ft end to end, longest span 63 ft: about 2.8 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built195076 years old
Length1011.2 ft308.2 m
Daily traffic4,654counted 2022
Last inspectedMarch 2023every 24 months

Location

StateOregon
CountyMultnomah
LocationBtwn N Tillamook/hancock
CarriesOr 99w Ramp
CrossesB-153 N Interstate AVE
Coordinates45.53731, -122.67481

Physical Characteristics

MaterialConcrete Continuous
DesignStringer/Multi-beam
Total Length1011.2 ft (308.2 m)
Max Span63.0 ft (19.2 m)
Deck Width35.1 ft (10.7 m)
Deck Area3297.7 sq m
Main Spans21
Year Built1950

Traffic

Avg Daily Traffic4,654 (2022)
Truck Traffic3%
Lanes On Bridge1
Lanes Under Bridge4

Inspection & Ownership

Last InspectionMarch 2023
Inspection FrequencyEvery 24 months
OwnerCity/Municipal Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number07115 01WX00106

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges