Structure 89004900000000 · Stephenson County, IL

River Road over US 20 Freeport Bypas

Carries River Road over US 20 Freeport Bypas, 2 Mi NE Of Freeport.

Overall conditionFair

Set by its lowest-rated component: Superstructure at 5 of 9.

How ratings work
Deck6/9 · Satisfactory
Superstructuresets the rating5/9 · Fair
Substructure6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT261 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 5/9 · sets the ratingSubstructure 6/9

261 ft end to end, longest span 107 ft: about 4 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built198442 years old
Length261.5 ft79.7 m
Daily traffic375counted 2024
Last inspectedDecember 2023every 24 months

Location

StateIllinois
CountyStephenson
Location2 Mi NE Of Freeport
CarriesRiver Road
CrossesUS 20 Freeport Bypas
Coordinates42.30906, -89.55898

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length261.5 ft (79.7 m)
Max Span107.0 ft (32.6 m)
Deck Width37.1 ft (11.3 m)
Deck Area900.6 sq m
Main Spans2
Year Built1984

Traffic

Avg Daily Traffic375 (2024)
Truck Traffic7%
Lanes On Bridge2
Lanes Under Bridge2

Inspection & Ownership

Last InspectionDecember 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number089004900000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.