Structure 60505000001529 · King County, WA

Road over Sunday Creek

Carries Road over Sunday Creek, 0.1mi E Of 52/54 Jct.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure and Substructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructuresets the rating6/9 · Satisfactory
Substructuresets the rating6/9 · Satisfactory
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
CAR · 15 FT117 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 6/9Substructure 6/9

117 ft end to end, longest span 81 ft. Lengths and the car on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built195670 years old
Length117.1 ft35.7 m
Daily traffic14counted 1991
Last inspectedAugust 2023every 24 months

Location

StateWashington
CountyKing
Location0.1mi E Of 52/54 Jct
CarriesRoad
CrossesSunday Creek
Coordinates47.21750, -121.44750

Physical Characteristics

MaterialSteel
DesignStringer/Multi-beam
Total Length117.1 ft (35.7 m)
Max Span81.0 ft (24.7 m)
Deck Width16.7 ft (5.1 m)
Deck Area182.1 sq m
Main Spans3
Year Built1956

Traffic

Avg Daily Traffic14 (1991)
Lanes On Bridge1

Inspection & Ownership

Last InspectionAugust 2023
Inspection FrequencyEvery 24 months
OwnerU.S. Forest Service
Historical SignificanceHistorical significance is not determined
Scour Critical4 — Foundations need monitoring
Structure Number060505000001529

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.