Structure 7687 · Limestone County, AL

Snake RD over Poplar CR

Carries Snake RD over Poplar CR, Sec14 T3s R6w.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructuresets the rating7/9 · Good
Substructuresets the rating7/9 · Good
Channelnot part of overall7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
CAR · 15 FT48 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 7/9Substructure 7/9

48 ft end to end, longest span 24 ft. Lengths and the car on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a tee-beam bridge.

Built196264 years old
Length47.9 ft14.6 m
Daily traffic575counted 2014
Last inspectedFebruary 2024every 24 months

Location

StateAlabama
CountyLimestone
LocationSec14 T3s R6w
CarriesSnake RD
CrossesPoplar CR
Coordinates34.77732, -87.13073

Physical Characteristics

MaterialConcrete
DesignTee Beam
Total Length47.9 ft (14.6 m)
Max Span24.0 ft (7.3 m)
Deck Width23.0 ft (7 m)
Deck Area102.2 sq m
Main Spans2
Year Built1962

Traffic

Avg Daily Traffic575 (2014)
Truck Traffic1%
Lanes On Bridge2

Inspection & Ownership

Last InspectionFebruary 2024
Inspection FrequencyEvery 24 months
OwnerCounty Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure Number007687

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.