Structure 33753 · Venango County, PA

SR 322 8th Street over Over Allegheny River

Carries SR 322 8th Street over Over Allegheny River, City Of Franklin.

Overall conditionFair

Set by its lowest-rated component: Superstructure and Substructure at 6 of 9.

How ratings work
Deck7/9 · Good
Superstructuresets the rating6/9 · Satisfactory
Substructuresets the rating6/9 · Satisfactory
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT922 FT OVERALL200 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 6/9 · sets the ratingSubstructure 6/9 · sets the rating

922 ft end to end, longest span 125 ft: about 2.6 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built198640 years old
Length921.9 ft281 m
Daily traffic9,567counted 2024
Last inspectedJuly 2023every 36 months

Location

StatePennsylvania
CountyVenango
LocationCity Of Franklin
CarriesSR 322 8th Street
CrossesOver Allegheny River
Coordinates41.38900, -79.81918

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length921.9 ft (281 m)
Max Span125.0 ft (38.1 m)
Deck Width39.4 ft (12 m)
Deck Area3,372 sq m
Main Spans9
Year Built1986

Traffic

Avg Daily Traffic9,567 (2024)
Truck Traffic5%
Lanes On Bridge2

Inspection & Ownership

Last InspectionJuly 2023
Inspection FrequencyEvery 36 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical5 — Stable for scour
Structure Number000000000033753

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.