Structure 2450 · Shelby County, IN

SR 9 over I-74 Eb/wb

Carries SR 9 over I-74 Eb/wb, 01.97 N SR 44.

Overall conditionFair

Set by its lowest-rated component: Deck at 5 of 9.

How ratings work
Decksets the rating5/9 · Fair
Superstructure6/9 · Satisfactory
Substructure6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT270 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 5/9 · sets the ratingSuperstructure 6/9Substructure 6/9

270 ft end to end, longest span 86 ft: about 4 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built1959rebuilt 2000
Length269.7 ft82.2 m
Daily traffic17,199counted 2022
Last inspectedDecember 2024every 24 months

Location

StateIndiana
CountyShelby
Location01.97 N SR 44
CarriesSR 9
CrossesI-74 Eb/wb
Coordinates39.55101, -85.77567

Physical Characteristics

MaterialConcrete Continuous
DesignStringer/Multi-beam
Total Length269.7 ft (82.2 m)
Max Span86.0 ft (26.2 m)
Deck Width76.4 ft (23.3 m)
Deck Area1915.3 sq m
Main Spans4
Year Built1959 (reconstructed 2000)

Traffic

Avg Daily Traffic17,199 (2022)
Truck Traffic3%
Lanes On Bridge4
Lanes Under Bridge5

Inspection & Ownership

Last InspectionDecember 2024
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number002450

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.