Structure 10916 · Clarion County, PA

Sr0066 Nb&sb over Sr0080 EB & Brush Run

Carries Sr0066 Nb&sb over Sr0080 EB & Brush Run, Greenville Pike No.1.

Overall conditionFair

Set by its lowest-rated component: Superstructure and Substructure at 5 of 9.

How ratings work
Deck6/9 · Satisfactory
Superstructuresets the rating5/9 · Fair
Substructuresets the rating5/9 · Fair
Channelnot part of overall6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT266 FT OVERALL50 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9Superstructure 5/9 · sets the ratingSubstructure 5/9 · sets the rating

266 ft end to end, longest span 75 ft: about 4 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a box-beam bridge.

Built1965rebuilt 2001
Length266.1 ft81.1 m
Daily traffic6,190counted 2024
Last inspectedMay 2023every 24 months

Location

StatePennsylvania
CountyClarion
LocationGreenville Pike No.1
CarriesSr0066 Nb&sb
CrossesSr0080 EB & Brush Run
Coordinates41.17671, -79.34848

Physical Characteristics

MaterialPrestressed Concrete
DesignBox Beam - Multiple
Total Length266.1 ft (81.1 m)
Max Span75.1 ft (22.9 m)
Deck Width65.3 ft (19.9 m)
Deck Area1613.9 sq m
Main Spans4
Year Built1965 (reconstructed 2001)

Traffic

Avg Daily Traffic6,190 (2024)
Truck Traffic8%
Lanes On Bridge4
Lanes Under Bridge2

Inspection & Ownership

Last InspectionMay 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour Critical8 — Stable, low risk
Structure Number000000000010916

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges