Structure 4C 874 · Salt Lake County, UT

Sr269wb.rp.to I15n over Uprr & 700 W

Carries Sr269wb.rp.to I15n over Uprr & 700 W, 500 South Viaduct In Slc.

Overall conditionFair

Set by its lowest-rated component: Deck and Substructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructure7/9 · Good
Substructuresets the rating6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT458 FT OVERALL100 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9 · sets the ratingSuperstructure 7/9Substructure 6/9 · sets the rating

458 ft end to end, longest span 177 ft: about 6 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built200026 years old
Length458.0 ft139.6 m
Daily traffic18,069counted 2017
Last inspectedAugust 2022every 24 months

Location

StateUtah
CountySalt Lake
Location500 South Viaduct In Slc
CarriesSr269wb.rp.to I15n
CrossesUprr & 700 W
Coordinates40.75811, -111.91009

Physical Characteristics

MaterialSteel Continuous
DesignStringer/Multi-beam
Total Length458.0 ft (139.6 m)
Max Span177.2 ft (54 m)
Deck Width42.3 ft (12.9 m)
Deck Area1800.8 sq m
Main Spans3
Year Built2000

Traffic

Avg Daily Traffic18,069 (2017)
Truck Traffic24%
Lanes On Bridge2

Inspection & Ownership

Last InspectionAugust 2022
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number4C 874

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.

Nearby Bridges