Structure 13692A0000000 · Thurston County, WA
Carries Trosper RD over I-5, 3.5 N Jct SR 121.
242 ft end to end, longest span 124 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a box-beam bridge.
| State | Washington |
| County | Thurston |
| Location | 3.5 N Jct SR 121 |
| Carries | Trosper RD |
| Crosses | I-5 |
| Coordinates | 46.99994, -122.91281 |
| Material | Prestressed Concrete Continuous |
| Design | Box Beam - Single/Spread |
| Total Length | 242.1 ft (73.8 m) |
| Max Span | 124.0 ft (37.8 m) |
| Deck Width | 73.2 ft (22.3 m) |
| Deck Area | 1645.7 sq m |
| Main Spans | 2 |
| Year Built | 1991 (reconstructed 2003) |
| Avg Daily Traffic | 21,420 (2012) |
| Truck Traffic | 5% |
| Lanes On Bridge | 5 |
| Lanes Under Bridge | 8 |
| Last Inspection | September 2023 |
| Inspection Frequency | Every 24 months |
| Owner | State Highway Agency |
| Historical Significance | Historical significance is not determined |
| Scour Critical | Not applicable |
| Structure Number | 0013692A0000000 |
Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."
A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.