Structure 8195 001 29923 · Multnomah County, OR

HWY 001 over SW Hood AVE

Carries HWY 001 over SW Hood AVE, 2.7 Mi N Of Multnomah Bvd.

Overall conditionFair

Set by its lowest-rated component: Deck and Superstructure at 6 of 9.

How ratings work
Decksets the rating6/9 · Satisfactory
Superstructuresets the rating6/9 · Satisfactory
Substructure7/9 · Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT214 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 6/9 · sets the ratingSuperstructure 6/9 · sets the ratingSubstructure 7/9

214 ft end to end, longest span 84 ft: about 3 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a tee-beam bridge.

Built195967 years old
Length213.6 ft65.1 m
Daily traffic112,736counted 2022
Last inspectedJanuary 2024every 24 months

Location

StateOregon
CountyMultnomah
Location2.7 Mi N Of Multnomah Bvd
CarriesHWY 001
CrossesSW Hood AVE
Coordinates45.49300, -122.67367

Physical Characteristics

MaterialConcrete Continuous
DesignTee Beam
Total Length213.6 ft (65.1 m)
Max Span84.3 ft (25.7 m)
Deck Width119.8 ft (36.5 m)
Deck Area2376.2 sq m
Main Spans3
Year Built1959

Traffic

Avg Daily Traffic112,736 (2022)
Truck Traffic10%
Lanes On Bridge7
Lanes Under Bridge2

Inspection & Ownership

Last InspectionJanuary 2024
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number08195 001 29923

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.