Structure 28771 · Hormigueros Municipio County, PR

Pr-2 over Pr-319

Carries Pr-2 over Pr-319, 0.50 Km. S.e. Hormigueros.

Overall conditionFair

Set by its lowest-rated component: Substructure at 6 of 9.

How ratings work
Deck7/9 · Good
Superstructure8/9 · Very Good
Substructuresets the rating6/9 · Satisfactory
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT824 FT OVERALL100 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 8/9Substructure 6/9 · sets the rating

824 ft end to end, longest span 119 ft: about 2.3 football fields. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built200818 years old
Length824.5 ft251.3 m
Daily traffic45,100counted 2017
Last inspectedMarch 2023every 24 months

Location

StatePuerto Rico
CountyHormigueros Municipio
Location0.50 Km. S.e. Hormigueros
CarriesPr-2
CrossesPr-319
Coordinates18.13583, -67.12611

Physical Characteristics

MaterialPrestressed Concrete
DesignStringer/Multi-beam
Total Length824.5 ft (251.3 m)
Max Span118.8 ft (36.2 m)
Deck Width93.2 ft (28.4 m)
Deck Area7136.9 sq m
Main Spans7
Year Built2008

Traffic

Avg Daily Traffic45,100 (2017)
Truck Traffic5%
Lanes On Bridge4
Lanes Under Bridge6

Inspection & Ownership

Last InspectionMarch 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceBridge is not eligible for the National Register
Scour CriticalNot applicable
Structure Number028771

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.