Structure 12825A0000000 · King County, WA

US 2 over Tunnel Creek

Carries US 2 over Tunnel Creek, 19.8 E Snohomish Co.

Overall conditionGood

Set by its lowest-rated component: Deck and Superstructure and Substructure at 7 of 9.

How ratings work
Decksets the rating7/9 · Good
Superstructuresets the rating7/9 · Good
Substructuresets the rating7/9 · Good
Channelnot part of overall8/9 · Very Good
0 failed4 poor6 fair9 excellent

Elevation

Side view, colored by inspection rating
SEMI-TRUCK · 72 FT170 FT OVERALL25 FT0ELEVATION · LENGTHS TO SCALE
Deck 7/9Superstructure 7/9Substructure 7/9

170 ft end to end, longest span 105 ft: about 2 semi-trucks nose to tail. Lengths and the semi-truck on the deck are drawn to the same scale. Each part is colored by its latest inspection rating. The inventory records lengths but not heights or the layout of the shorter spans, so those are drawn as typical for a multi-beam bridge.

Built198541 years old
Length169.9 ft51.8 m
Daily traffic2,795counted 2023
Last inspectedAugust 2023every 24 months

Location

StateWashington
CountyKing
Location19.8 E Snohomish Co
CarriesUS 2
CrossesTunnel Creek
Coordinates47.71803, -121.12264

Physical Characteristics

MaterialPrestressed Concrete Continuous
DesignStringer/Multi-beam
Total Length169.9 ft (51.8 m)
Max Span105.0 ft (32 m)
Deck Width39.0 ft (11.9 m)
Deck Area616.4 sq m
Main Spans2
Year Built1985

Traffic

Avg Daily Traffic2,795 (2023)
Truck Traffic5%
Lanes On Bridge2

Inspection & Ownership

Last InspectionAugust 2023
Inspection FrequencyEvery 24 months
OwnerState Highway Agency
Historical SignificanceHistorical significance is not determined
Scour Critical5 — Stable for scour
Structure Number0012825A0000000

How Bridge Ratings Work

Inspectors rate each major part of a bridge (the deck you drive on, the superstructure of beams that holds it up, and the substructure of piers and abutments beneath) on a 0–9 scale. A bridge's overall condition is its lowest of those ratings, so one deteriorated component makes the whole bridge "poor."

0Failed
1Imminent failure
2Critical
3Serious
4Poor
5Fair
6Satisfactory
7Good
8Very good
9Excellent
Good · lowest component 7–9
Fair · lowest component 5–6
Poor · lowest component 0–4

A poor rating is not a closure. It means the bridge is flagged for priority repair or replacement; bridges judged unsafe are closed or posted with weight limits. The waterway (channel) rating is reported, but it does not count toward the overall classification.